Strabag signs seven Romanian rail contracts worth 179.45m lei
STRABAG România signed seven CFR SA rail contracts on 26 November 2026 worth 179.45m lei, covering bridges, culverts and eight tunnels on lines including Bumbești-Livezeni, with completion due 2027-28.
· 2 min journey

Calling at
- Seven contracts signed 26 November 2026, total volume 179.45 million Romanian lei
- Six lots on Bumbești-Livezeni worth 129.27m lei ex-VAT; completion 2027-2028
- Adjud-Siculeni bridge at km 53+480: ~50m lei, 20-month duration including planning
- Eight tunnels totalling 2.07 km on Bumbești-Livezeni section
- STRABAG share price €105.30 at Lang & Schwarz on 27 November 2026
STRABAG România signed seven contracts worth 179.45 million Romanian lei on 26 November 2026 to plan and execute works on the Romanian rail network, with contract partner CFR SA, the national railway company. Romanian trade publication Agenda Constructiilor reported the awards.
The bulk of the work targets the historic Bumbești-Livezeni section of the Filiași-Livezeni line. Six contracts cover the rehabilitation of two railway bridges, four culverts and eight tunnels. The seventh contract covers a railway bridge on the Adjud-Siculeni line in the Galați regional network.
What does the work change for operations?
The eight tunnels on the Bumbești-Livezeni section total 2.07 km in length. The planned measures aim to stabilise existing structures, reduce their vulnerability to natural events, and cut the current restrictions on speed, axle load and loading gauge. Beyond renewing the infrastructure, the project therefore targets safer and more efficient rail operations on a line where physical constraints currently limit what trains can carry and how fast they can run.
Contract terms and timetable
The six lots under the Craiova regional railway directorate carry a volume of 129.27 million lei excluding VAT. Planning phases run four to six months per lot, depending on the lot; construction takes six to eleven months. Completion is scheduled for 2027 and 2028, depending on the individual start date of each package.
The seventh contract, signed on 26 November 2026, covers the rehabilitation of a bridge at kilometre 53+480 on the Adjud-Siculeni line. That project has a volume of around 50 million lei and a duration of 20 months, including planning and execution.
STRABAG România bid as the sole tenderer. Subcontractors and technical supporters include Baicons Impex, ISPCF, SPIACT Craiova and Strabag Rail of the Czech Republic.
Financing comes under Romania's transport programme for 2021 to 2027, combined with state funds and CFR SA's own resources.
How does this fit Strabag's order book?
For investors, the contracts slot into Strabag's infrastructure strategy. The Austrian group had already reported in November dynamic growth in the first nine months and a high order backlog. The new rail contracts expand the regional project scope, but the order volume alone allows no conclusion about group earnings — the announcement is an award, not a measured result.
Strabag SE trades under ISIN AT000000STR1. The real-time share price at Lang & Schwarz stood at €105.30 on Friday, 27 November 2026, at 12:18.
Whether the 2027 and 2028 completion dates hold will depend on the staggered start of construction across the six Craiova lots, with the 20-month Adjud-Siculeni bridge package running on its own clock.
via ad-hoc-news.de (Source)
More from Olivia Hart
Show full bio
Market editor covering people, launches and day-to-day practice in Rail industry news and analysis at Mainline Report.
409 articles
Connecting services · Related articles
- 09:25
Croatia signs €677m contract to double-track Dugo Selo–Novska line
- 00:59
Správa železnic Earmarks CZK 5.4 Billion for Project Preparation
- 00:54
GPT Infraprojects' South African arm wins ₹385 crore sleeper deal
- 02:50
Nurminen–Tarros deal extends Nordic block train to Mediterranean
- 10:54
Ploiesti to Replace Ageing Tram Fleet with 20 New Vehicles Backed by €36m EIB Loan