Poland maps 350 km/h Y Line and Baltic corridors to 2035
Poland's Port Polska programme sets a 2032 opening for the 350 km/h Warsaw–Łódź Y Line, with branches to Poznań and Wrocław by 2035 and new corridors to Berlin, Czechia and Lviv.
· 3 min journey

Calling at
- Warsaw–Łódź high-speed section scheduled to open in 2032; western Y Line branches planned by 2035.
- New lines designed for 350 km/h, though commercial speeds may be lower depending on rolling stock and energy costs.
- Up to 250 km/h expected on the CMK southern section from 2027; current Polish passenger maximum is 200 km/h on Warsaw–Gdańsk.
- Proposed corridors include a Baltic–Czechia route at 250 km/h and an eastern line from Warsaw towards Lviv in Ukraine.
- Routes remain indicative; alignments to be fixed through further studies by Port Polska with PKP PLK.
Poland has published a high-speed rail programme that would put trains on new lines designed for 350 km/h, with the first section — Warsaw to Łódź via the planned new airport — scheduled to open in 2032.
The scheme, branded the Port Polska programme, names the Y Line as its first corridor. It runs from Warsaw and the planned airport hub to Łódź, then branches west towards both Poznań and Wrocław, with completion of both branches planned by 2035.
What does the plan actually change?
For now, measured capability is modest. Poland currently runs passenger trains at up to 200 km/h on the Warsaw–Gdańsk route. That is the ceiling today.
From 2027, speeds of up to 250 km/h are expected on the existing southern section of the Central Railway Main Line (CMK, Poland's core north–south trunk built for high-speed operation). That upgrade is the near-term, buildable step. Everything else in the programme is a proposal.
A gap runs through the announcement itself. Lines will be designed for 350 km/h, but commercial operating speeds may come in lower, depending on rolling stock, energy costs and operational requirements. Design speed is a civil-engineering figure; the timetable figure is what passengers and energy bills respond to. The programme does not yet say which speed it will deliver.
The international corridors
The Y Line's proposed extension from Poznań towards Szczecin via Gorzów Wielkopolski includes a connection towards Berlin. That matters operationally. It would create an alternative to the existing Warsaw–Berlin route via Rzepin, and by taking some passenger flows off that path it could release additional capacity for freight on Railway Line 3 — the existing international corridor towards Germany that freight operators already use heavily.
A new Baltic–Czechia corridor, designed for up to 250 km/h, would link Gdańsk, Bydgoszcz, Poznań and Wrocław, continuing via Wałbrzych to the Czech border. It threads the country's western backbone into the Czech network.
In the east, a high-speed corridor is planned from Warsaw via Siedlce, Lublin and Zamość towards Lviv in Ukraine. Its geometry points at eventual cross-border integration with Ukraine's network, though the source states the route only as a plan.
Further domestic lines
Beyond the Y Line, several corridors carry the 350 km/h design figure:
- Warsaw–Gdańsk
- Wrocław–Opole–Katowice–Kraków
- Poznań–Wrocław
A new Warsaw–Kraków connection via Kielce is also planned, with a design speed exceeding 300 km/h. On present network geography, that would shortcut the classic route via the CMK and Zamkowiec junction, though the source gives the routing, not the business case.
The programme adds several further corridors designed for up to 250 km/h, covering eastern Poland, the Baltic coast and additional north–south connections across the country.
Whose plan is this?
The proposals form part of Poland's Integrated Railway Network, developed by Port Polska in cooperation with PKP PLK, the state infrastructure manager. That institutional pairing matters: PLK controls the existing network whose capacity the new lines would relieve, and its involvement signals that the proposals sit inside national planning rather than outside it.
One caveat governs the entire map. The proposed routes remain indicative, and precise alignments will be determined through further studies. Corridors on a planning map have changed before alignment work begins; the 2032 and 2035 dates are programme targets, not committed delivery dates backed by procurement.
No fleet order, funding amount or supplier contract accompanies the announcement, so the cost and rolling-stock questions — the ones that decide whether 350 km/h design becomes 300, 250 or 200 km/h in service — remain open.
The next hard milestones to watch are the CMK's 250 km/h operation from 2027 and the alignment studies that turn the indicative Y Line routes into engineered ones.
via railmarket.com (Source)
More from Priya Raman
Show full bio
Staff writer covering companies, deals and strategy in Rail industry news and analysis at Mainline Report.
413 articles
Connecting services · Related articles
- 22:35
Warsaw–Łódź high-speed bidder list cut to five of eight
- 12:55
CPK launches Port Polska as its rolling stock leasing arm
- 10:18
Poland's High-Speed Rail can help deliver Europe's vision
- 13:25
PKP Intercity to invest €6.1bn as Polish rail travel hits 30-year high
- 00:49
Poland's €143bn rail plan adds 4,700 km but leaves out freight