Škoda hands over final RegioJet trainset as 23-unit fleet completes

Škoda has delivered the last of 23 RegioJet trainsets — 54 dual-system vehicles for the Ústí nad Labem Region, with all units due in service from the December timetable change.

· 3 min journey

Calling at

  1. Škoda completed delivery of 23 RegioJet trainsets (54 vehicles) on 19 November.
  2. Fleet comprises 15 two-car units (142 seats) and eight three-car units (228 seats).
  3. Trains run at 160 km/h with ETCS; first units entered service on 1 July 2026.
  4. All 23 trainsets are scheduled for operation from the December timetable change.
  5. Dual-system units were built with Škoda's Ostrava plant for the Ústí nad Labem Region.

Škoda Group has completed delivery of the last of 23 RegioJet trainsets, closing out a 54-vehicle order built for regional services in the Ústí nad Labem Region of Czechia. The final unit arrived on 19 November, and operator RegioJet intends to have all 23 trains in passenger operation from the December timetable change.

The fleet splits into two configurations: 15 two-car units and eight three-car units. Škoda Group's Ostrava plant participated in the manufacture of the trainsets, which are dual-system vehicles — meaning they can draw power from two different electrification systems — suited to mixed regional infrastructure.

What does the fleet offer passengers?

Capacity differs sharply between the two variants. A two-car trainset carries 142 seats; a three-car unit offers 228. Maximum speed is 160 km/h, and every train in the fleet is fitted with ETCS (the European Train Control System, the standard signalling equipment required for cross-border and domestic operation across much of Europe).

On-board equipment listed by the supplier covers the full set of amenities now standard for competitive regional rail in central Europe:

  • air conditioning
  • Wi-Fi
  • power sockets and USB charging points
  • step-free boarding for passengers with reduced mobility
  • dedicated spaces for bicycles and pushchairs

What does this change for the Ústí nad Labem Region?

The region gains a uniform, fully delivered fleet in place of phased roll-outs and mixed stock. The first of the new trains entered passenger service on 1 July 2026, giving roughly five months of revenue operation before the final unit was handed over. From December, the region's regional services can be planned around a known pool of 23 trainsets with identical performance parameters — 160 km/h top speed, ETCS fitment and dual-system capability — rather than around whatever rolling stock happens to be available.

For passengers, the practical outcomes are capacity and consistency. The 228-seat three-car units more than half-exceed the seating of the two-car variant, which gives the operator flexibility to match train length to demand on individual routes. Buggy and bicycle spaces, level access and onboard connectivity address the segments — families, commuters, leisure travellers with bikes — that regional operators across Europe identify as growth markets.

Supplier claims against the record

The delivery figures come from the supplier's announcement of fleet completion: 23 trainsets, 54 vehicles in total across the two configurations, final handover on 19 November. The arithmetic is consistent — 15 two-car sets contribute 30 vehicles and eight three-car sets contribute 24, totalling 54 — and the in-service date of 1 July 2026 for the first units is stated as fact rather than projection.

The one forward-looking element is the December target for full-fleet operation. That is a schedule commitment, not a measured result, and it depends on driver training, depot capacity and ETCS commissioning falling into place before the timetable change. RegioJet and the Ústí nad Labem Region will judge the order a success when all 23 trainsets run to diagram, not when the last one leaves the factory gate.

With delivery now closed, attention shifts to fleet performance in daily service — availability, reliability and the actual deployment pattern of two-car versus three-car sets across the region's routes from the December timetable onward.

via railmarket.com (Source)

More from Priya Raman

Priya Raman

Show full bio

Staff writer covering companies, deals and strategy in Rail industry news and analysis at Mainline Report.

405 articles

Connecting services · Related articles

  1. 20:39

    Škoda adds 16 Sofia metro trainsets in €149m contract

  2. 22:23

    Teleste lands €40m on-board systems deal for Copenhagen S-bane fleet

  3. 22:23

    ÖBB and Siemens unveil Railjet M multiple-unit for Alpine routes

  4. 02:50

    Škoda Unveils Second-Generation Battery Electric Train at InnoTrans 2026

  5. 24:49

    VinSpeed awards Siemens Mobility $1.15bn turnkey deal for 10 Velaro Novo trains

« Previous serviceNext service »