Portal North Bridge enters full service, retiring 116-year-old span
Both tracks of the $1.6 billion Portal North Bridge are in service after a Nov. 16 cutover, retiring a 116-year-old swing bridge that chronically delayed Northeast Corridor trains.
· 4 min journey

Calling at
- Both tracks of the new Portal North Bridge entered full service on Nov. 16 after a five-week second-track cutover.
- The old Portal Bridge retires after 116 years over the Hackensack River and is scheduled for dismantling in 2027.
- NJ Transit awarded the construction contract, worth nearly $1.6 billion to Skanska/Traylor Bros PNB Joint Venture, its largest ever.
- The FTA invested $926 million; a January 2021 Full Funding Grant Agreement secured $766.5 million.
- The project spans 2.44 miles of the Northeast Corridor and is part of the Gateway Program aiming to double rail capacity between Newark and New York.
Both tracks of the new Portal North Bridge entered full service on Nov. 16, ending rail operation of the 116-year-old Portal Bridge over the Hackensack River and removing one of the Northeast Corridor's most chronic sources of delay for NJ Transit and Amtrak customers.
New Jersey Gov. Mikie Sherrill, NJ Transit and Amtrak officials gathered in Kearny, N.J., to mark the completion, which followed what NJ Transit describes as a successful five-week cutover process on the second and final track.
"New Jersey commuters deserve to get to work on time and get home to their families without a century-old bridge holding up the entire Northeast Corridor," Sherrill said. "With both tracks of the Portal North Bridge now in service, we are eliminating a major source of delays and delivering the reliable transportation our residents and economy depend on."
The governor called the completion "a major step forward for Gateway and proof of what we can accomplish when we stay focused on getting things built."
What does the change mean for passengers?
The new structure is a fixed span that does not open for marine traffic. Trains no longer stop for bridge openings, which the agencies identify as an enduring source of major service disruptions on the corridor. NJ Transit lists three operational outcomes:
- Improved reliability and fewer bridge-related delays
- Increased operational resilience along the Northeast Corridor
- A modern structure designed to support future capacity growth
Service changes tied to the cutover have ended. Regular NJ Transit weekend service resumed Nov. 15. Weekday diversions of Midtown Direct service to Hoboken and cross-honoring options have ended, with full service resuming between Newark and Secaucus. NJ Transit directs customers to timetables for current schedules.
The first track cutover began Feb. 13 and finished March 15, bringing the initial track into service while the old swing bridge kept operating. Work on the second track began Oct. 9 and concluded Nov. 16. The old Portal Bridge is scheduled for dismantling in 2027.
"Today, our customers begin benefiting from a generational investment that will make their trips more reliable for decades to come," NJ Transit President and CEO Kris Kolluri said. "The new Portal North Bridge permanently removes a chronic source of delays, allowing marine traffic to pass beneath the bridge without interrupting the trains carrying our customers to work, home and everywhere in between."
Kolluri acknowledged that both cutover projects "asked a great deal" of customers and thanked them for their patience.
Who paid, and who built it?
The U.S. Department of Transportation, the states of New Jersey and New York, and Amtrak funded the project. In January 2021, then-New Jersey Gov. Phil Murphy announced a Full Funding Grant Agreement securing $766.5 million in Federal Transit Administration funding for construction.
FTA Region 2 Administrator Michael Culotta put the administration's investment at $926 million. "The new fixed bridge is a game changer for workers and residents in New Jersey, and it means less delays during our commutes, more family time and better access to education, health care and job opportunities in our region," Culotta said.
In October 2021, Murphy and NJ Transit announced a construction contract of nearly $1.6 billion awarded to Skanska/Traylor Bros PNB Joint Venture — the single largest construction award in NJ Transit's history, according to the agency.
"The cutover is complete, and Portal North Bridge is ready to deliver," Amtrak Interim President Byl Herrmann said, crediting crews and the partnership with NJ Transit for "more reliable, faster service" for both operators' customers.
How does it fit into Gateway?
The project spans 2.44 miles of the Northeast Corridor and includes retaining walls, deep foundations, concrete piers, structural steel bridge spans, rail systems, demolition of the existing bridge and related works. It forms a component of the broader Gateway Program, which aims to eventually double rail capacity between Newark and New York.
Gateway Development Commission CEO Tom Prendergast called the completion "a milestone for the history books" and said the commute that hundreds of thousands of daily riders have awaited "is on the horizon." With the Hudson Tunnel Project advancing alongside it, the commission says the region is on track for doubled rail capacity between New Jersey and New York.
via njtransit.com (Original)
More from Olivia Hart
Show full bio
Market editor covering people, launches and day-to-day practice in Rail industry news and analysis at Mainline Report.
394 articles
Connecting services · Related articles
- 24:44
Portal North Bridge cutover starts Oct. 9, five weeks of disruption
- 08:20
New Jersey DOT Opens Freight-Rail Grant Application Window
- 01:10
NJ Transit reliability decline cannot be blamed on Amtrak alone, study finds
- 07:25
New Jersey Opens Applications for $25M in Rail Freight Assistance Grants
- 17:02
FRA grants NCDOT $550 million for Raleigh–Richmond S-Line