HS2 starts deck-laying on Curzon approaches with 125-tonne gantry crane

HS2 Ltd has begun the last major phase of civil engineering on Birmingham's Curzon approaches: an 18-month, gantry-crane-driven deck-laying operation across five viaducts.

· 3 min journey

HS2 Prepares to Begin Work on Curzon Approaches
HS2 Prepares to Begin Work on Curzon Approachesanalogicus / pixabay

Calling at

  1. A 125-tonne gantry crane will spend 18 months laying deck slabs across five interconnected viaducts at the Curzon approaches.
  2. Deck slabs are manufactured at Balfour Beatty VINCI's factory in Kingsbury, Warwickshire, which previously produced Delta Junction segments for four years.
  3. Night closures on the Lawley Middleway (A4540) run from 21 November to 6 December, between 22:00 and 06:00.
  4. The works cover the final mile of HS2's entry into Birmingham city centre.

HS2 Ltd has started the final major phase of civil engineering on the Curzon approaches, the last mile of the high-speed line's entry into Birmingham, with a 125-tonne gantry crane set to spend 18 months laying concrete deck slabs across five interconnected viaducts.

The crane has already been lifted into position above the Lawley Middleway viaduct. From there it will work outward, laying slabs one at a time as it progresses from Lawley Middleway to Curzon 2, Curzon 1 and finally Duddeston Junction viaduct. Once the decks are complete, HS2 says, the elevated gateway into Birmingham will be structurally complete — though track-laying and systems work will still follow before any train runs.

What changes on the ground?

Engineers begin laying the concrete slabs later this week to form solid decks on each structure, ahead of track installation. The slabs come from Balfour Beatty VINCI's purpose-built factory in Kingsbury, Warwickshire. That production line has now switched over from its previous task: four years of manufacturing segments for the Delta Junction viaducts. The shift signals that the joint venture's precasting capacity is moving to the city-centre end of the route.

Greg Sugden, HS2 Ltd's Head of Delivery for the Curzon Approaches, framed the milestone in measured terms.

"This is a huge moment for the Curzon approaches team, as we begin what is essentially the last major phase of civil engineering works on this section of the route," Sugden said. "It's a test of skill and precision, as we must ensure that when the gantry crane arrives at each structure, we're ready for the deck installation works to begin."

He confirmed the timeline: around 18 months to lay the decks, after which the structure is complete. That is a claim about civil works only; HS2 Ltd did not state when track, signalling or station fit-out at Curzon Street would finish, and the announcement contains no dates for train services.

Malik Kayatas, Section Manager at Balfour Beatty VINCI, described the method: "A 125-tonne gantry crane will begin installing deck slabs along a series of interconnected viaducts in Birmingham this week. Sitting on top of the structures, it will move outwards from the city centre on an 18-month journey, marking the next exciting phase of this project."

Which roads close, and when?

To protect the public and site workers while slabs are laid above roads and walkways, HS2 will impose temporary night closures on the Lawley Middleway (A4540) between Garrison Circus and Curzon Circus:

  • Northbound only, 22:00 to 06:00 each night, from Saturday 21 November until Sunday 6 December.
  • Full closure in both directions, 22:00 to 06:00 each night, from Wednesday 25 November until Wednesday 2 December.
  • Southbound only, 22:00 to 06:00 each night, from Thursday 3 December until Sunday 6 December.

All closures fall inside a two-week window, and none extend beyond 6 December according to the announced schedule. Drivers using the A4540 inner ring road at night should expect disruption concentrated in that period.

What remains unsaid

The announcement gives no cost figure for the approaches phase, no slab production rate, and no updated completion date for the Birmingham leg of the railway as a whole. The 18-month deck-laying programme, if it holds, would put structural completion of the approaches within roughly a year and a half — a schedule claim that, like every HS2 milestone before it, will be tested against delivery.

via railway-news.com (Source)

More from Amara Osei

Amara Osei

Show full bio

News editor covering technology and product news in Rail industry news and analysis at Mainline Report.

403 articles

Connecting services · Related articles

  1. 24:59

    California High-Speed Rail Project Marks 66 Completed Structures

  2. 16:34

    California high-speed rail reaches 66 completed structures

  3. 24:49

    Melbourne Airport Rail Stage 2 Advances Toward 2031 Opening

  4. 23:24

    California high-speed rail completes six Central Valley structures

  5. 19:30

    MTA opens scoping on 125 Street crosstown tunnel extension

« Previous serviceNext service »