Derwent Valley Line closes for nine days as 4.6km track renewal begins

Network Rail closes Derby–Matlock for nine days from 14 December to renew 4.6km of track, 3,509 sleepers and 6,400 tonnes of ballast at three sites.

· 2 min journey

UK: Passengers Urged to Plan Journeys Ahead of Work Along Derwent Valley Line
UK: Passengers Urged to Plan Journeys Ahead of Work Along Derwent Valley Line652234 / pixabay

Calling at

  1. No trains between Derby and Matlock from 14 to 22 December, a nine-day closure.
  2. 4.6km of new rail, 3,509 sleepers and 6,400 tonnes of ballast will be installed at three sites.
  3. Eight engineering trains will be used, including a New Track Construction train.
  4. Replacement buses will call at all stations; Derby–Sheffield services are unaffected.

No trains will run between Derby and Matlock for nine days from Saturday 14 December as Network Rail renews more than 4.5km of track on the Derwent Valley Line.

The closure, running from 14 to 22 December, covers three work sites at Matlock Bath, Cromford and near Whatstandwell station. Rail replacement buses will operate between Derby and Matlock for the duration, calling at all stations. Services between Derby and Sheffield remain unaffected.

Network Rail first flagged the work in mid-November, reminding passengers to plan journeys ahead of the blockade.

What does the work involve?

The programme delivers a full renewal of the track infrastructure at the three sites:

  • 4.6km of new rail
  • 3,509 sleepers
  • 6,400 tonnes of ballast

Network Rail expects the renewal to cut future maintenance needs and reduce the overall risk of delays on the route, which carries both passenger and freight traffic.

Eight engineering trains will support the work, including a New Track Construction train that lays new rails and sleepers as it travels. That machine allows a greater volume of track renewal within the nine-day closure than conventional methods would permit.

What does this change for passengers?

Between 14 and 22 December, travellers between Derby and Matlock must use the replacement bus service. The buses serve every intermediate station on the route, including the stops closest to the work sites at Matlock Bath, Cromford and Whatstandwell. Derby–Sheffield services continue to run as normal, so through journeys via Derby are not disrupted beyond the connection change.

The line reopens to trains once the blockade ends on 22 December, with the renewed track intended to deliver smoother, more reliable journeys for both passenger and freight operators.

Why the renewal is needed

The rail, sleepers and ballast being replaced have reached the end of their working life, according to Network Rail. Renewing them in a single extended blockade rather than through piecemeal weekend possessions concentrates the disruption into one period and reduces the frequency of future unplanned maintenance interventions on the East Midlands route.

Eric Larocque, Network Rail operations director, said: "This investment will renew key sections of track along the Derwent Valley Line, helping us provide a safer, more reliable railway for passengers and freight operators."

He added: "By replacing rail, sleepers and ballast that have reached the end of their working life, we're improving the resilience of the East Midlands route and reducing the need for unplanned maintenance."

Larocque also acknowledged the impact on travellers: "We'd like to thank passengers and residents for their patience while this important work is carried out, and we're sorry to those whose journeys will be affected."

The Derwent Valley Line renewal forms part of Network Rail's wider effort to lift reliability across the East Midlands route. Once normal services resume after 22 December, passengers and freight operators should see fewer speed restrictions and delay-inducing track faults on the renewed sections between Derby and Matlock.

via railway-news.com (Source)

More from Olivia Hart

Olivia Hart

Show full bio

Market editor covering people, launches and day-to-day practice in Rail industry news and analysis at Mainline Report.

394 articles

Connecting services · Related articles

  1. 07:08

    £7M Rail Investment Between Newcastle and Scotland Underway

  2. 14:05

    Signalling failure between Ore and Eastbourne disrupts Southern services

  3. 22:54

    TfW Faces Four-Week North Wales Bus Replacement Test in £25m Closure

  4. 24:54

    First refurbished Tangara EMU back on Sydney's T4 line

  5. 24:44

    MBTA Orders October Service Outages Across Eight Lines for Infrastructure Push

« Previous serviceNext service »