Stadler CHARME coaches enter service on Astana–Almaty route

Stadler CHARME coaches began running between Astana and Almaty on 11 November, with full deliveries to 2030 and €60m of Kazakh plant investment planned by 2031.

· 2 min journey

Stadler CHARME enters service in Kazakhstan
Stadler CHARME enters service in KazakhstanBen Garratt / unsplash

Calling at

  1. CHARME coaches entered service on 11 November on the ~1,300 km Astana–Almaty route
  2. Fleet deliveries run until the end of 2030
  3. Stadler has invested over €10m in its Astana plant, plus more than €28m this year in new workshops
  4. Total Kazakh investment from 2023 to 2031 will reach at least €60m
  5. Coaches are rated for -50°C to +45°C and run on both electrified and non-electrified lines via generator cars

Stadler's CHARME passenger coaches entered revenue service on 11 November on the roughly 1,300 km route between Astana and Almaty, with deliveries of the full fleet scheduled to continue until the end of 2030.

The fleet mixes several interior configurations. Compartment coaches carry 40 berths, open-plan sleeping coaches offer 58 berths, and PRM coaches — vehicles adapted for passengers with reduced mobility — provide 18 berths, dedicated accessible spaces and a bistro area.

What does the fleet change for operations?

The vehicles are designed to work in temperatures from -50°C to +45°C, a range that matches the Kazakh climate from winter steppe to summer heat. Generator cars supply power on non-electrified lines, so the same coaches can run across both electrified and diesel-only sections of the national network. That removes a traditional constraint on long-distance consists, which otherwise need to be reshuffled at traction change points.

Onboard equipment is built around passenger comfort and security:

  • individual lighting and temperature controls at each berth;
  • 220V sockets plus USB and USB-C charging points;
  • Wi-Fi and CCTV;
  • increased luggage capacity.

Where are the coaches built?

Production takes place at Stadler's plant in Astana under a localisation programme. The original agreement between the Swiss manufacturer and its Kazakh partners included technology transfer from Switzerland alongside the purchase and modernisation of an existing local facility.

Stadler has invested more than €10 million in reconstructing the plant. Kazakh specialists received training at the company's European production sites before the facility ramped up.

The Astana site now handles a full production chain rather than simple assembly. Its scope covers steel car body welding and painting, manufacture of electrical equipment and underfloor components, bogie production (the wheeled underframes carrying the coach body), installation of pneumatic and electrical systems, and final assembly with commissioning.

How much money is going into Kazakhstan?

Stadler is investing more than €28 million this year alone in new aluminium car body welding and painting workshops. According to the company, the expanded facility will be the first highly automated plant of its kind in Central Asia.

The site currently employs more than 700 people. Stadler expects the expansion to add around 100 jobs. Total investment in Kazakhstan between 2023 and 2031 will reach at least €60 million, the company says — a figure that covers both the initial reconstruction and the new aluminium workshops but which remains a company projection rather than a fully spent amount.

Measured against that timeline, the 11 November entry into service marks an early milestone. Fleet deliveries stretching to the end of 2030 suggest a steady replacement cycle on Kazakhstan's principal north–south corridor rather than a single-step rollout, and the generator-car arrangement indicates the fleet is intended for network-wide flexibility from the outset.

via railmarket.com (Source)

More from Priya Raman

Priya Raman

Show full bio

Staff writer covering companies, deals and strategy in Rail industry news and analysis at Mainline Report.

391 articles

Connecting services · Related articles

  1. 21:04

    More than 100 Stadler sleeping coaches enter service in Kazakhstan

  2. 08:15

    Stadler to build two electro-diesel rack locomotives for MVR

  3. 09:08

    Stadler shows Flirt Nordic Express cars bound for Norway's long-distance routes

  4. 24:44

    LTG Link to start Stadler FLIRT revenue service on 22 October

  5. 12:53

    Stadler’s Weinfelden commissioning hall targets 2028 operation

« Previous serviceNext service »