Dakar TER reaches Blaise Diagne airport as 55 km line completes

Senegal extended Dakar's TER 19 km to Blaise Diagne International Airport on September 28, completing a 55 km, 160 km/h route ahead of the 2026 Youth Olympic Games.

· 3 min journey

Calling at

  1. Dakar TER was extended 19 km to Blaise Diagne International Airport on September 28, taking the route to 55 km.
  2. The TER has carried nearly 100 million passengers since Phase 1 opened on December 27, 2021, running up to 196 trains per day at 98% punctuality.
  3. Phase 2 cost estimates rose from about CFAFr208bn to around CFAFr276bn per APIX, with the government citing more than CFAFr300bn.
  4. The CAF fleet grew to 22 Coradia Polyvalent electro-diesel trainsets with seven additional four-car sets ordered in 2023.
  5. The line is double-track, electrified at 25 kV 50 Hz and equipped with ETCS Level 2 and GSM-R.

Senegal extended Dakar's Train Express Régional by 19 km to Blaise Diagne International Airport on September 28, completing a 55 km standard gauge route just ahead of the Dakar 2026 Youth Olympic Games.

The inauguration was attended by Minister of Land Transport & Air Transport Serigne Abdoul Ahad Ndiaye, Minister of Infrastructure Déthié Fall and Minister of Employment Idrissa Samb.

The second phase adds a double-track, 160 km/h alignment electrified at 25 kV 50 Hz and equipped with ETCS Level 2 and GSM-R. The extension links Dakar's city-centre rail spine directly to the country's main international airport.

How is the existing network performing?

SETER, the SNCF subsidiary that operates the line, reports the TER has carried nearly 100 million passengers since the 36 km first phase opened between Dakar and Diamniadio on December 27, 2021. The service runs up to 196 trains per day with a punctuality rate of 98%.

Those figures come from the operator itself; they position the airport extension as the scaling of a network already carrying heavy commuter demand rather than a standalone airport rail link.

Who built Phase 2, and at what cost?

The principal infrastructure contract, worth CFAFr108.4bn, went to a consortium of Eiffage Génie Civil, Eiffage Rail, Turkey's Yapi Merkezi and Senegalese contractor CSE in May 2023.

The airport station, connected to the terminal by a 200 m pedestrian walkway, was built by Turkey's Summa under a separate CFAFr8bn contract.

The railway systems package covering signalling, ETCS, GSM-R and electrification was awarded for CFAFr76.3bn to INEO SCLE Ferroviaire and GTS France in September 2023. Following corporate changes and the evolution of the consortium, the works were delivered by the Equans/Hitachi Rail M2 group.

Phase 2 costs rose substantially during implementation. The original estimate stood at about CFAFr208bn. Public works agency APIX puts the final cost at around CFAFr276bn, while the government cited more than CFAFr300bn at the inauguration — a gap of roughly CFAFr25bn between the official accounts.

What is the fleet?

CAF received a contract in 2023 to supply seven additional four-car Coradia Polyvalent electro-diesel trainsets for Phase 2, expanding the fleet to 22 sets. The trains were built at Reichshoffen, with Alstom supplying major equipment.

The electro-diesel configuration gives the operator flexibility where full electrification is not yet in place on the extended route.

Who financed the project?

Funding came from several international institutions and bilateral sources:

  • Islamic Development Bank: €100m initially, plus €40.25m in supplementary financing and CFAFr8bn for the airport station
  • African Development Bank: US$74m
  • Arab Bank for Economic Development in Africa: US$50m
  • West African development bank BOAD: CFAFr35bn
  • France: a €150m package agreed subsequently for project completion

What comes next?

With the airport link now open months before the Dakar 2026 Youth Olympic Games, SETER faces the task of absorbing expected visitor traffic on a network already running nearly 200 trains a day, while the government's cost accounting for Phase 2 — CFAFr276bn against CFAFr300bn-plus — remains to be reconciled.

via Railway Gazette International (Source)

More from Olivia Hart

Olivia Hart

Show full bio

Market editor covering industry trends and analytics at Mainline Report.

292 articles

Connecting services · Related articles

  1. 09:25

    Croatia signs €677m contract to double-track Dugo Selo–Novska line

  2. 24:44

    EBID clears USD 100 million for Kano–Maradi Phase II rolling stock

  3. 08:35

    PRASA commits R13bn to Durban signalling and uMlazi corridor

  4. 08:05

    PRASA commits R13bn to Durban signalling and uMlazi corridor

  5. 02:44

    Alstom and Siemens land São Paulo rail signalling contracts

« Previous serviceNext service »