Coradia Max Delays Push Alstom to €954m Half-Year Loss
Alstom swung to a €954m net loss for H1 2026/27 as Coradia Max delays in Germany bit, despite orders rising 5% to €11bn and backlog reaching €111bn. A €2bn deleveraging plan is under way.
· 3 min journey

Calling at
- Alstom reported a €954m net loss for H1 2026/27, versus a €220m profit a year earlier
- Adjusted EBIT fell to a €396m loss from a €580m profit, driven by Coradia Max industrialisation and homologation delays in Germany
- Orders rose 5% to €11bn, book-to-bill hit 1.2, and backlog reached €111bn at end-September
- TransPennine Express ordered 29 five-car battery-electric trains plus maintenance worth about €1.1bn combined
- Organisational restructuring decisions are expected before the end of 2026, alongside a €2bn deleveraging objective
Alstom has posted a net loss of €954m for the first half of its 2026/27 financial year, a swing from a €220m profit a year earlier, with project execution failures on the Coradia Max platform in Germany identified as the principal cause.
Sales for the six months ended 30 September 2026 reached €9.33bn, up 3% year on year, of which 2% was organic growth. The top line grew. The bottom line collapsed. Adjusted EBIT (earnings before interest and tax, excluding one-off items) fell to a loss of €396m, against a profit of €580m in the first half of 2025/26.
What went wrong on Coradia Max?
The manufacturer attributed the deterioration primarily to industrialisation problems — the stage at which a validated design is converted into repeatable series production — and an extended homologation timeline for Coradia Max, its regional double-deck train platform supplied to German operators. Homologation is the formal safety and technical approval process a new train must pass before entering passenger service.
Other projects being delivered for and from Germany were also affected. Alstom said it has reinforced its testing programme and is implementing technical solutions and retrofit measures on the affected fleets.
The commercial picture tells a different story from the industrial one. Orders received rose 5% to €11bn, producing a book-to-bill ratio (orders divided by sales, a measure of demand coverage) of 1.2. The order backlog stood at €111bn at the end of September.
What does this change for customers and shareholders?
For operators, the near-term risk is delivery slippage: longer homologation for Coradia Max means later entry into service for German regional fleets, and retrofit work adds engineering time to programmes already in execution. For shareholders, the immediate effect is a €1.17bn swing in net result and a stretched path back to margin.
CEO Martin Sion framed the response in operational and financial terms. He said: "First-half results reflect project execution challenges recently identified. We are acting decisively on the key levers to improve execution, including operating model and commercial strategy, while pursuing a €2 billion deleveraging objective to reinforce the balance sheet."
Sion also pointed to a delivery milestone as evidence of underlying capability: "The entry into commercial service of our very-high-speed platform Avelia Horizon earlier this month demonstrates the capabilities of our teams and the strength of Alstom's technology. We are committed to transforming Alstom into a best-in-class company in our industry."
Order intake spread across three continents
The €11bn order intake included several sizeable awards:
- TransPennine Express, UK: an agreement for 29 five-car battery-electric trains plus long-term maintenance, worth approximately €1.1bn combined
- VIA Rail Canada: 313 Adessia rail cars
- Africa and Middle East: rail modernisation and maintenance contracts in South Africa, Saudi Arabia and Egypt
The spread of new business across the UK, Canada, Africa and the Gulf indicates the German execution problems have not dented demand for Alstom's products, at least in the order book.
Execution first, then restructuring
Alstom has made improving project execution its main operational priority. The measures it listed are specific:
- Tighter cost and procurement controls
- Faster resolution of technical issues
- Greater accountability for project managers
- Simpler internal processes
Beyond these operational fixes, the group is reviewing its organisational and operational structures, with decisions expected before the end of 2026. That timeline points to a structural announcement — potentially covering business line configuration or management layers — within roughly two months of the results publication.
The company's own framing separates measured results from what remains projection. The half-year loss, the EBIT swing and the order figures are recorded facts. The €2bn deleveraging objective, the execution improvements and the benefits of the reorganisation are commitments whose delivery will be tested in the second half and in the full-year figures. With a €111bn backlog providing revenue visibility, Alstom's immediate test is narrower than demand: it is whether the Coradia Max industrialisation and homologation fixes, plus the retrofit programme, convert a full pipeline into reliably delivered trains.
via railway-news.com (Source)
More from Priya Raman
Show full bio
Staff writer covering companies, deals and strategy in Rail industry news and analysis at Mainline Report.
405 articles
Connecting services · Related articles
- 23:23
Alstom posts €954m half-year loss as Coradia Max slips to 2028
- 09:54
Alstom signs €460m Riyadh metro train order despite margin warning
- 08:35
InnoTrans 2026: Alstom, Siemens and Škoda lead €1bn-plus rolling stock deals
- 24:44
Rheinmetall to acquire Alstom's Kassel locomotive factory
- 09:15
Alstom completes S$1·16bn Singapore metro fleet renewal