Rail contractors face a 2030 signalling gap and a shrinking workforce

ETCS covered just 12,400 km, or 10% of TEN-T, at end-2024. Remote possession systems promise more work per shift, but network-wide savings remain unproven.

· 5 min journey

More Work, Fewer People. Getting More from Every Shift
More Work, Fewer People. Getting More from Every ShiftJon Handley / unsplash

Calling at

  1. About 12,400 km, or 10% of TEN-T, had ETCS at end-2024; the core network stood at 17%.
  2. February 2026's Third ERTMS Work Plan projects only about half of the 2030 core-network target on current plans.
  3. €345 billion is the Commission's estimated investment requirement for planned TEN-T high-speed lines by 2040.
  4. Network Rail runs 8% of possessions under T3-A or T3-D, which permit 6% more work, and targets 80% by 2029.
  5. A Sussex mobile-maintenance-train trial added six maintenance hours over four nights and annualised to £425,000 in savings.

By Amara Osei

European Rail Traffic Management System (ERTMS) trackside signalling, known as ETCS, covered about 12,400 km, or 10% of the Trans-European Transport Network (TEN-T), at the end of 2024, against a 2030 deadline for the core network.

How far behind is ERTMS deployment?

The European Commission requires ERTMS on the core network by 2030 and on the rest of TEN-T by 2050. At the end of 2024, 17% of the core network had ERTMS equipment. The Third ERTMS Work Plan, published in February 2026, projects only about half of the 2030 core target on current plans.

That projection places a substantial share of the core network behind current delivery plans as 2027 planning begins. Infrastructure managers and contractors must produce more work within the same limited number of track possession windows and overnight access periods.

What does the EU rail plan require?

The EU High Speed Rail Plan, published in November 2025, was revisited at InnoTrans 2026, alongside renewed attention to the ERTMS backlog. Its wider TEN-T objective is to connect all EU capitals and major cities by 2040.

The Commission estimates that completing the planned high-speed network within TEN-T will require €345 billion of investment by 2040. The analysis does not break that figure down by country, corridor or signalling system, so the spending envelope cannot by itself demonstrate delivery capacity.

Can a shrinking workforce deliver more work?

In the Netherlands and the United Kingdom, one third of rail workers are expected to retire during the 2020s. In Germany, 38% of the workforce is over 50. UNIFE has highlighted a shortage of skills for all rail works across Europe.

Under the EU's traffic ambition, freight trains are expected to double and passenger trains to triple in the coming years, adding maintenance demand to a smaller workforce. Those are projections rather than measured traffic additions, and the source provides no timetable for them.

Productivity must therefore rise, according to the underlying analysis, and the proposed remedy is digitalisation. That argument requires more than a supplier's selected operating examples: each possession still has to deliver more work without reducing safety or extending closures.

Where does possession time go?

The analysis reports that safety preparation can consume 25% of a typical Dutch maintenance shift, equal to one hour in a four-hour shift. It says much of the preparation remains manual, including placing flags, detonators and short-circuiting devices.

Reclaiming that hour could increase work within the same closure. By contrast, each additional night of work reduces rail capacity and costs at least €25,000. The source does not say how many additional nights individual projects require, which limits any calculation of network-wide capacity gains.

What do remote systems deliver in practice?

Network Rail used a mobile maintenance train inside a single protection zone in Sussex and gained six additional maintenance hours across four night shifts. Annualised, the reported saving was £425,000. This is one operating example, not a European performance rate; the analysis provides no equivalent measurements from other countries and does not disclose the equipment cost needed to judge the return.

Network Rail says 8% of possessions currently use T3-A or T3-D arrangements, which permit 6% more work. It plans to reach 80% by 2029. The target is clear; the delivery risk is substantial because it requires more possessions to use a new protection method.

With remote equipment operation or signal disconnection, the Fatality Weighted Index falls from 0.898 under traditional protection to 0.306 with engineering controls, a reduction of about two thirds. The index measures risk, not observed fatalities, so it cannot establish two thirds fewer accidents.

In Germany, the supplier reports supporting remote operation of point machines disconnected from the power supply, with growing interest in remote earthing of overhead lines and securing level crossings. Combining remote track closure, worksite demarcation and overhead-line earthing can allow a team to begin work within five minutes of the last train passing.

Here the supplier moves from evidence to promise. Dual Inventive states: “Safety and productivity do not have to be at odds with one another. Our experience is that they move in the same direction.” The Sussex example and the index change support those claims at case level, but neither establishes the outcome for the wider TEN-T network.

What must happen next?

For infrastructure managers, the economic incentive may matter less than completing the same work in less time and with fewer people on site. The figures indicate a service outcome: more work per possession. They do not provide a network-wide benefit.

Dual Inventive says: “The direction is settled. What remains open is the pace.” The practical test is whether managers can measure time lost on each possession, adopt remote protection at scale and report comparable cost, capacity and safety results.

The company has offered personalised calculations, but the analysis publishes no common method for translating possession-level gains into network-wide capacity.

By 2040, Europe must deliver more infrastructure, faster maintenance and common signalling with an ageing workforce and rising traffic. Remote protection offers a measurable route to higher output per shift, yet its case rests on a Sussex trial, a UK rollout target and supplier-selected examples rather than an audited European total.

By 2029 and 2030, the decisive evidence will be measured possession-level time losses and safety results across networks, not further isolated trials.

via railway-news.com (Source)

More from Amara Osei

Amara Osei

Show full bio

News editor covering technology and product news in Rail industry news and analysis at Mainline Report.

403 articles

Connecting services · Related articles

  1. 08:07

    European Commission releases 'Connecting Europe through high-speed rail'

  2. 24:44

    ERA calls for ERTMS spec freeze as 17% of EU core network fitted

  3. 16:38

    Stability, not money, is the barrier to EU high speed rail

  4. 16:00

    European Rail Policy: The Road Ahead for the Continent's Network

  5. 17:30

    EU lawmakers target 2040 for rail push to rival air travel

« Previous service