Málaga–Madrid AVE services could return 6–7 December, drivers say

AVE drivers expect Málaga–Madrid high-speed services to resume on 6–7 December after Urda crash repairs, but Adif withholds a date pending test runs and judicial conditions stretch the works to 14 days.

· 4 min journey

Provisional reopening date put forward for Malaga-Madrid high-speed rail service
Provisional reopening date put forward for Malaga-Madrid high-speed rail serviceWolfgang-1958 / pixabay

Calling at

  1. High-speed services between Málaga and Madrid could resume around 6–7 December, per AVE drivers' estimates; Adif has given no official date.
  2. Adif must replace just over 40 metres of track, overhead line and signalling within a 400-metre work area at Urda.
  3. The 28 October collision between a Renfe AVE and an Iryo train cut the Málaga–Madrid corridor on 28 October.
  4. Renfe, Iryo and Ouigo provisionally resume ticket sales on 13 December, with earlier opening if Adif approves.
  5. Double-unit S-112 trainsets would offer up to 700 seats on peak days to offset reduced service frequency.

High-speed trains between Málaga and Madrid could resume commercial service around 6 or 7 December, according to AVE drivers' working assumptions, although infrastructure manager Adif refuses to commit to any date until safety testing on the repaired track is complete.

The estimate, circulating in railway circles and described by experts as "feasible", rests on a tight sequence of steps. Drivers expect Adif to finish track repairs on Friday 4 November. A test-run period would then begin, using completely empty trains — only the driver and a few technicians on board — to verify the safety and reliability of the repaired section. Those tests need at least one to two days. Commercial services would follow.

An Adif spokesperson kept the door firmly shut on deadlines. "We began work last Saturday, 21 November, and once this is complete, testing will be required before the corridor can be brought back into service," the spokesperson said, declining to give dates "as a matter of caution". Adif, Spain's rail infrastructure body, holds the final say on whether trains may run.

What does the reopening change for passengers?

The 28 October crash at Urda — in which a Renfe AVE train rear-ended an Iryo service — severed the high-speed link between Málaga and Madrid. Since then, travellers, notably the thousands of Málaga residents who work in the Spanish capital and return regularly to visit family, have had to fall back on plane, car or bus.

When services return, the timetable will be thinner than before. The ministry of transport reported days ago that fewer services will run each day, with the cuts falling mainly on late-afternoon departures. The final services of the day will be cancelled to lengthen the overnight window for track maintenance.

To offset the lost seats, the proposal is to run double-unit trains — two trainsets coupled together — carrying up to 700 seats on Renfe's S-112 fleet, deployed on days of peak demand such as weekends and public holidays, provided loadings justify it.

Demand itself is expected to be soft in the first days back. The provisional dates fall in the middle of the December bank holiday weekend, when passengers with travel plans will mostly have completed their journeys on the Friday or Saturday before. The return leg on 8 December, and even 9 December, a working day, could prove the stronger traffic days.

Why the repair is taking longer than the damage warrants

The physical damage is limited. Adif workers must replace just over 40 metres of track, overhead line and signalling and safety systems, within a work area extending to 400 metres. Under normal conditions, that would take no more than ten days, and the scope is far smaller than the damage at Adamuz from an earlier incident.

Instead, the works are on track to take 14 days if the drivers' latest estimates hold. The delay stems from the judicial supervision imposed by Judge Ortiz Tiliakou, who is investigating the collision. The judge authorised reconstruction and repair in the crash area, but attached strict conditions covering the period before, during and after the work.

Before repairs began, the prosecution and the investigating judge ordered Adif to carry out a topographical survey and to draw up a complete inventory of all damaged components. Once the works are finished, Adif must submit a precise list of every component repaired or replaced, for inclusion in the case file. Sources close to the process believe these forensic requirements will extend repair times.

Ticket sales remain anchored to 13 December

State operator Renfe is holding to its original schedule and will not sell tickets for AVE and Avlo (its low-cost brand) services until Sunday 13 December. The company has consistently stated that if Adif approves train running earlier, it will open sales for the specified date. The private operators on the corridor, Iryo and Ouigo, have followed Renfe's lead and also provisionally set 13 December for resuming sales.

The practical outcome, then, is a corridor caught between two clocks: drivers working to a 6–7 December reopening, an operator ready to sell tickets sooner if cleared, and an infrastructure manager that will not pronounce until empty test trains have run over rebuilt track and the judge's documentation requirements are met. If the December bank holiday dates hold, the first meaningful test of restored capacity will come on the 8 December return-peak day.

via surinenglish.com (Source)

More from Priya Raman

Priya Raman

Show full bio

Staff writer covering companies, deals and strategy in Rail industry news and analysis at Mainline Report.

413 articles

Connecting services · Related articles

  1. 08:57

    Madrid–Andalucía reopening set for reduced services after Urda crash

  2. 13:58

    Urda crash repairs begin: Madrid–Málaga AVE faces December restart

  3. 11:05

    Madrid–Barcelona high-speed services resume after train fire

  4. 19:54

    Malaga commuter rail strike called off after Spanish cabinet approves safety decree

  5. 01:28

    Judge clears Urda track rebuild but puts Adif under strict court supervision

« Previous serviceNext service »