Gothenburg RoRo Terminal targets 10% annual rail growth
GRT targets 10% annual rail freight growth after a track rebuild nearly doubled yard storage at Arken, though port-wide rail volumes rose just 2% so far in 2026.
· 3 min journey

Calling at
- GRT targets approximately 10% annual growth in rail freight volumes.
- A track rebuild at Arken created about 4,000 m² of extra space, nearly doubling yard storage capacity.
- Arken handles around 25 rail shuttles per week across seven electrified tracks totalling 3,360 metres.
- Port of Gothenburg rail container volumes rose 2% year-on-year to 403,000 TEU in January–September 2026.
- RoRo quay cargo volumes rose 5% in the first half of 2026 versus the same period in 2025.
Gothenburg RoRo Terminal (GRT) has set a target of lifting its rail freight volumes by approximately 10% per year, betting on a track-layout rebuild that almost doubled storage capacity at its Arken Intermodal Terminal.
The figure is a projection, not a measured result. What has been measured is the physical expansion: rebuilding one of the terminal's through tracks created roughly 4,000 m² of additional space for trailers and intermodal units, increasing the available area by about 5% while nearly doubling yard storage capacity.
GRT operates the RoRo terminal and the adjacent Arken Intermodal Terminal at the Port of Gothenburg, handling transfers between rail, road and sea. Trailers account for around half of its rail volumes. The remainder comprises tank containers, standard containers and swap bodies.
How much capacity does Arken have?
The Arken terminal currently handles approximately 25 rail shuttle services per week. Its infrastructure consists of seven electrified tracks with a combined length of 3,360 metres — an average of 480 metres per track — and it has an annual handling capacity of approximately 100,000 transport units.
The newly created space allows GRT to absorb peaks in traffic with fewer internal cargo movements, and gives operators greater flexibility in train loading and unloading. The terminal also coordinates shunting and train schedules with railway operators and the Swedish Transport Administration, particularly during seasonal disruptions affecting rail infrastructure — an operational detail the port itself flags as a constraint on throughput.
Is the wider port traffic keeping pace?
The growth target coincides with, but does not yet match, actual traffic trends across the Port of Gothenburg. During January–September 2026, rail container volumes rose by 2% year-on-year to 403,000 TEU — a modest increase relative to the 10% annual growth GRT says it is targeting at its own terminals.
Approximately 60% of the port's containers move to or from inland destinations by rail, a share supported by the Railport Scandinavia network. That network connects Gothenburg with inland terminals across Sweden, including locations in Småland, Skåne and northern Sweden, giving Swedish importers and exporters access to the port's maritime connections.
What else has changed on the ground?
GRT has expanded its terminal infrastructure beyond the storage rebuild in recent years:
- Operations at Arken have been integrated with the adjacent RoRo terminal.
- Additional transshipment facilities for steel and forest products have improved the handling of railborne industrial cargo.
- Cargo volumes handled over the RoRo terminal's quays increased by 5% in the first half of 2026 compared with the same period in 2025.
The 5% rise in quay-handled volumes is the clearest measured signal that demand is moving in the direction of the 10% ambition. Whether the doubled yard capacity translates into growth at that rate will depend on shuttle volumes, seasonal rail disruptions and the pace of inland terminal demand.
GRT has not disclosed the investment cost of the track rebuild, nor a timeline for when the 10% annual growth rate is expected to be reached.
via railmarket.com (Source)
More from Amara Osei
Show full bio
News editor covering technology and product news in Rail industry news and analysis at Mainline Report.
403 articles
Connecting services · Related articles
- 14:35
Rostock Port moves to expand rail infrastructure at intermodal terminal
- 07:20
Rail Cargo Group adds 70 wagons for electric vehicle transport
- 01:24
RCG moves 13,800 tonnes by MOBILER through Hamm in H1 2026
- 24:59
Baltic Hub commissions two RMG cranes, lifts Gdańsk rail capacity to 1.2M TEU
- 24:49
CargoBeamer boosts capacity on three intermodal routes