Al Maktoum airport targets 2032 opening with three rail plans
Al Maktoum airport is planned to open commercially in 2032, backed by Metro, airport express and Etihad Rail plans, with final capacity above 260 million passengers and 12 million tonnes of cargo.
· 4 min journey

Calling at
- Al Maktoum is planned to begin commercial operations in 2032, with the Red Line extension due in 2031.
- An airport express and Etihad Rail are also planned, with Etihad Rail stops targeted within five years.
- The completed hub is designed for more than 260 million passengers and 12 million tonnes of cargo annually, five times DXB’s size.
- DXB recorded 50.4 million passengers in the first nine months of 2026 and is forecast above 70 million for the year.
- Dubai Airports sees DXB traffic potentially reaching 100 million by the end of 2027.
Al Maktoum International Airport is planned to begin commercial operations in 2032, with final-phase capacity of more than 260 million passengers and 12 million tonnes of air cargo each year.
Dubai has approved the Metro extension serving the airport, and Dubai Crown Prince Sheikh Hamdan has said Red Line services will begin in 2031. Etihad Rail stops are planned within five years, while a proposed airport express (a dedicated rail connection) would link Al Maktoum with Dubai International Airport (DXB).
Paul Griffiths, chief executive officer of Dubai Airports, set out the broader ground-transport plan at the Big 5 Global event on Monday, 23 November 2026. His remarks tie the rail programme to the emirate’s effort to develop land and air infrastructure around the new hub and ease passenger traffic.
What changes for airport passengers?
- Red Line extension: Approved expansion, with Sheikh Hamdan giving 2031 as the service start year.
- Airport express: Planned direct rail service between Al Maktoum and DXB, without a published opening date.
- Etihad Rail: Planned service into the new terminal, with stops within five years, but the announcement supplied no detailed timetable or fleet commitment.
Only the Metro extension has both an announced start date and approval described in the source. The airport express and Etihad Rail remain proposals outlined by Dubai Airports; their contribution to passenger capacity cannot yet be treated as operating infrastructure. Named services are not timetables.
Griffiths called all three highly helpful to customers travelling to and from the airport. The announcement supplied no rolling-stock order (a purchase of trains and related equipment), detailed timetable or fleet plan against which to check the delivery claims.
Griffiths said the ground service offer must match the technical advance of the airport itself. “The whole ecosystem will provide a seamless, frictionless journey from start to finish where people will just feel that the whole design of the airport process has been transformed from what we perceive today,” he said.
His vision includes collecting bags from passengers’ homes and delivering them to the airport once technology and transport systems are fully integrated. That is an operating concept, not a committed product: no operator, supplier, start date or cost accompanies it, and full integration remains a precondition.
Located in Dubai South, Al Maktoum currently handles cargo aircraft. Once complete, it is intended to replace DXB as Dubai’s main aviation hub within the next decade. Dubai Airports describes the result as the world’s largest aviation hub and five times DXB. The passenger and cargo capacities are design targets for the final phase, not present throughput.
The scale requires more than a terminal. The surrounding urban and transport ecosystem must move from Dubai’s northeast to the southwest corner of the city.
“We’re not just building an airport. We have to build the communities, relocate people, build apartments, houses, malls, schools,” Griffiths said. He described the work as effectively transplanting an entire sector of the city from one end of Dubai to the other.
On his account, airport capacity and urban development must advance together: the surrounding housing, schools, retail and transport network have to expand with the terminal. The announcement did not set out the cost, phasing or relocation timetable for that work.
Traffic baseline and transition
Measured performance at DXB provides a baseline for the transition. The existing hub recorded 50.4 million passengers in the first nine months of 2026 and is expected to exceed 70 million for the year despite travel disruptions caused by the war. The first figure is measured; the second is a forecast.
Griffiths expects a repeat of the post-Covid travel boom and said passenger traffic could reach 100 million by the end of 2027. The 100 million figure is a management forecast, not a capacity commitment or observed result.
On the announced timetable, rising traffic at DXB and Al Maktoum’s eventual replacement of that hub describe a staged transfer rather than an abrupt handover.
The next test is whether the three rail plans become a funded delivery programme before the first commercial phase opens in 2032. The final design’s 260-million-passenger scale depends on ground access moving from policy language into operating timetables, alongside the housing, community and baggage systems that Griffiths expects to make the journey seamless.
via khaleejtimes.com (Source)
More from Priya Raman
Show full bio
Staff writer covering companies, deals and strategy in Rail industry news and analysis at Mainline Report.
405 articles
Connecting services · Related articles
- 07:40
Dubai Metro's Dh2bn airport extension puts DWC 25–30 minutes from Marina
- 24:39
Etihad Rail to Launch Passenger Services Between Abu Dhabi and Dubai
- 12:55
UAE Opens Freight Rail Service Between Fujairah and Abu Dhabi
- 24:54
Egypt targets July 2027 launch for Ain Sokhna–Marsa Matrouh high-speed line
- 14:48
UAE President rides Etihad Rail as Dubai station opens